Newsflash from Sunday, 25 January 2026:

The construction of the Selinari Tunnel, a critical part of Crete’s Northern Road Axis (BOAK), is proving far more complex than originally planned. Beneath the mountains near Selinari, engineers are battling difficult geological conditions that are significantly affecting the pace—and timeline—of this major infrastructure project.
Why the Selinari Tunnel Matters
The Selinari tunnels are designed to improve road safety and traffic flow on one of Crete’s most heavily used and dangerous sections of highway, connecting Selinari to Agios Nikolaos. Once completed, the project is expected to reduce accidents, shorten travel times, and support tourism and local development in eastern Crete.
Geology Takes Center Stage
According to engineers working on the project, the geological composition of the mountain is the main factor slowing progress. Excavation teams are encountering clay-rich, highly fractured, and weathered material, which requires constant stabilization to prevent collapses.
This means tunneling cannot proceed at a steady pace. As conditions change—sometimes within just a few meters—construction crews must adjust their approach to ensure safety.
Three Levels of Tunnel Support
Depending on the rock and soil encountered, engineers apply three different categories of structural support to the tunnel walls and ceiling. In more unstable sections, heavy support is required, which can triple excavation time compared to areas where lighter reinforcement is sufficient.
As a result, providing an accurate completion date for the tunneling phase remains extremely difficult.

Progress So Far
Work on the twin Selinari tunnels began from June 2024. To May 2025:
– One tunnel has been excavated to approximately 190 meters
– The second has reached about 120 meters
The total length of each tunnel is close to 2 kilometers. Crews from the east are expected to eventually meet teams from the west, where excavation is progressing faster due to more stable rock formations that allow for controlled blasting.
Meeting Point Still Uncertain
Project supervisors estimate that the two sides could meet following spring, depending on how geological conditions evolve.
Adding to the project’s scope, a third tunnel, approximately 750 meters long, is expected to begin excavation soon. This tunnel will be built south of the old Vrachasi tunnel and is intended to further improve safety along the route.

Delays Already Accumulating
Despite efforts to stick to the original schedule, the project has already exceeded its initial timelines by eight months to one year. Extensions are now considered unavoidable, given the technical challenges underground.

A Complex but Crucial Project
While the slow progress may test public patience, engineers stress that safety must come first. The Selinari Tunnel project highlights how unseen geological conditions can dramatically shape major infrastructure works—and why careful, methodical construction is essential.
Once completed, the tunnels are expected to transform travel in the region, offering a safer and more reliable road connection for residents, businesses, and visitors alike.