News brief from Tuesday, 17 November 2026 (voak/boak, Hersonissos):

There is no confirmed change to travel arrangements on the BOAK section between Hersonissos (Χερσόνησος), in eastern Crete, and Neapoli (Νεάπολη). The latest development concerns how the project’s public contribution and construction milestones are arranged; the revised contract must still pass a legality review by Greece’s Court of Audit, according to ZarpaNews.
The proposed public contribution remains €90 million. Its funding mix would change: €56,999,545 is assigned to the Recovery and Resilience Facility, under the “Greece 2.0” programme, while €33,000,455 would come from national resources through the Public Investment Programme. ZarpaNews reports that the European Commission gave its approval in July and August 2026.
Payments tied to construction progress
Rather than being described only as a funding total, the contribution is divided into three payments linked to specified work. The largest, €56,999,545, is conditional on submitting all studies and surveys, completing phases of excavation and temporary support for tunnel S1, and finishing the structural frame of bridge G6.
A second payment of €15,000,455 would follow completion of the corresponding excavation phases at tunnel S3. The final €18 million is linked to work at tunnel S2. The revised milestones replace targets that could no longer be met within the original schedule, the report says.
A later availability date
The planned date for making the services available has moved from 21 April 2027 to 11 July 2028; the final deadline has shifted to 11 July 2029. ZarpaNews attributes the delay to construction areas being handed over late, and says the contractor was not responsible. The change meant that the original technical milestones, especially those concerning tunnels S2 and S3, could not be achieved within the Recovery and Resilience Facility’s deadlines. The facility required the project’s physical scope to be completed by 31 December 2026.
The contract would also reset how exceptional insurance costs are handled. The threshold for applying that category is to rise from 50% to 100% of the base cost for adjustable insurance. Any difference—whether an additional expense or a benefit—would be accounted for in full, rather than at 85%. The stated aim is to preserve the allocation of risk and the project’s classification outside the general government sector by Eurostat.
What does this mean for visitors or expates?
The report does not announce closures, diversions or other immediate effects on road users. As a practical precaution, visitors and residents planning to use the corridor can check current traffic information before setting out; the contract changes alone do not establish that journeys will be affected.