The new Kastelli Airport in Crete is 76 per cent complete, with a target completion date of November 2028, and progress on the BOAK

The new Kastelli Airport has taken a major step forward with the signing of a contract for air traffic control systems; the motorway link to the new airport on Crete is taking shape; and construction is progressing on all sections of the major motorway project.

flughafen kastelli may 26
Passenger terminal at Kastelli Airport under construction (photo taken in mid-May this year)

Crete’s New Kastelli Airport Reaches 76% Completion—Opening Target Set for November 2028

Construction of the new Heraklion International Airport at Kastelli has reached 76% completion, with authorities maintaining their target of beginning operations in November 2028.

Infrastructure and Transport Minister Christos Dimas and Deputy Minister Nikos Tachiaos recently toured the construction site alongside MPs, local government representatives and regional stakeholders. The visit provided an overview of the work completed so far, including the airport’s buildings, technical systems and supporting infrastructure.

aerodromio kasteliou

Control tower already complete

Officials were briefed on the installation of the airport’s navigation and operational systems. The control tower is already ready, while work continues across the terminal and other facilities.

Minister Dimas said construction was progressing at a particularly advanced stage. He stressed that the priority is to maintain the project schedule and ensure that the airport is ready to welcome passengers in November 2028.

%CE%B5%CE%B9%CE%BA%CF%8C%CE%BD%CE%B1 Viber 2026 08 07 09 36 41 684.jpg

A major project for Crete

The new airport is being designed as a high-specification international gateway for Crete. Once operational, it is expected to support the island’s tourism sector while providing modern facilities for residents and visitors.

Deputy Minister Tachiaos described Crete as the flagship of Greek tourism and said the island deserves an exceptional airport. He also highlighted the importance of related projects, including the road connection currently under construction.

The Kastelli airport is part of a wider period of infrastructure development across Crete, with major projects reshaping the island’s transport network and supporting its long-term economic growth.

kasteli aerodromio 4 1280x960 1

New Kastelli Airport Takes Major Step Forward with Air Navigation Systems Contract

%CE%B5%CE%B9%CE%BA%CF%8C%CE%BD%CE%B1 Viber 2026 08 07 10 34 17 894.jpg

A contract for the supply and installation of air navigation systems at Crete’s new Heraklion International Airport in Kastelli has been signed, marking another important milestone for the major infrastructure project.

The agreement was signed at a special ceremony held at the airport construction site in the presence of Infrastructure and Transport Minister Christos Dimas, Deputy Minister Nikos Tachiaos and Infrastructure Secretary-General Dimitris Anagnopoulos. Crete Regional Governor Stavros Arnaoutakis and Heraklion MPs also attended the event.

Systems designed to support safe operations

The contract covers modern air navigation systems that will help ensure the safe and efficient management of air traffic. Their installation is considered essential to the airport’s operational readiness and future international operations.

The agreement was concluded between the Heraklion International Airport, the Hellenic Civil Aviation Authority and Spanish technology company Indra.

November 2028 opening target maintained

Minister Dimas said the government’s goal remains for the airport to become fully operational in November 2028. He noted that construction has reached approximately 76%, with progress expected to rise to around 85% in the coming months.

Officials also highlighted the progress of the road connection to Crete’s Northern Road Axis, which will provide a crucial link to the new airport. At the same time, discussions continue over the location of the radar facility at Papoura, an issue currently under review by Greece’s Council of State.

When completed, the Kastelli airport is expected to become one of Greece’s most modern airports and a key gateway for residents and visitors to Crete.

Crete’s New Airport Link Takes Shape as BOAK Tunnel Construction Advances

voak tounel

Construction of the tunnel linking Crete’s new Heraklion International Airport at Kastelli with the Northern Road Axis of Crete (BOAK) is making steady progress.

The project includes a twin-bore tunnel approximately three kilometres long. Once completed, it will provide a faster and more direct connection between the BOAK and the new airport in the Pediada area.

More than 500 metres excavated

According to the latest project information, more than 500 metres of the tunnel have already been excavated, while overall progress has exceeded 30%. Completion is currently scheduled for autumn 2028, ahead of the airport’s planned opening.

The tunnel has replaced the open-road solution originally included in the project’s environmental approvals. The design was modified after archaeological discoveries were made in the Petrianos Lakkos area. The change was incorporated into the concession agreement signed on March 2, 2026.

€69.1 million commitment

The Ministry of Infrastructure and Transport has committed €69.11 million to cover part of the tunnel’s cost. The funding includes access works, excavation-front development, studies, personnel and equipment mobilisation, materials, completed works, acceleration costs and the fee of the Independent Engineer.

TERNA is carrying out the construction on behalf of the concession company, GEK TERNA–GMR.

Work is also continuing on the wider airport road connection. Approximately 15 of the planned 18 kilometres have effectively been completed, further strengthening the transport links that will serve the new airport when it opens.

Crete’s Northern Road Axis: Construction Accelerates Across All Sections of Major Motorway Project

2 800x534

Active construction is now taking place along the entire length of Crete’s Northern Road Axis (BOAK), with significant progress reported across multiple sections spanning from Chania to Agios Nikolaos.

Infrastructure and Transport Minister Christos Dimas completed a comprehensive inspection of BOAK construction sites across the island, confirming that work is advancing according to schedule. The tour included stops in Chania, Rethymno, Heraklion and Agios Nikolaos and was accompanied by Deputy Minister Nikos Tachiaos and Infrastructure Secretary-General Dimitris Anagnopoulos.

New motorway sections on track for completion

Works on the new BOAK bypasses around Chania, Rethymno and Heraklion are progressing as planned and are expected to open to traffic soon. These major urban bypass routes will significantly improve traffic flow and road safety near Crete’s three largest cities.

The Neapoli–Agios Nikolaos section has reached an advanced stage of construction. The first approximately 10 kilometres of the new motorway—running between Agios Nikolaos and Neapoli—are expected to be handed over to traffic in the coming weeks.

Comprehensive road-safety improvements underway

Alongside motorway construction, the government is implementing urgent road-safety improvements across 131 kilometres of the existing BOAK, stretching from Kissamos to Heraklion. These interventions are a priority until the new motorway opens.

Safety upgrades include resurfacing work, improved road markings and signage, installation of safety barriers, enhanced street lighting, vegetation management and other technical measures designed to increase visibility and reduce accident rates.

Three sections have already been completed: Chania–Kolymbari, Rethymno–Geropotamos and Heraklion Wastewater Treatment Plant–Linopeгамata. The remaining four high-risk sections—Souda–Georgioupoli, Petres–Atsipopoulo, Kissamos–Kolymbari and Geropotamos–Heraklion Wastewater Treatment Plant—are targeted for completion by late August.

Transforming Crete’s transport future

Minister Dimas said the government’s goal is to deliver a modern, safe and efficient motorway to Crete’s residents. Once complete, the BOAK will fundamentally change travel patterns across the island and serve as a powerful catalyst for regional development.

BOAK Progress Wins Praise as Major Crete Road Project Reaches Key Milestones

streckenplan boak
Route map of the new BOAK between Hersonissos and Neapoli.

Infrastructure and Transport Minister Christos Dimas has expressed satisfaction with the progress of the Northern Road Axis of Crete (BOAK), as construction sites continue operating across the island.

The concession agreement for the main project was signed on May 9, 2025. Since then, work has expanded across several locations in Chania, Rethymno and Heraklion. The Chania–Kissamos option was also activated seven months earlier than initially planned.

Important milestones achieved

Among the project’s latest milestones is the breakthrough of tunnel S2, which is approximately 1,980 metres long. The excavation was completed despite significant geotechnical challenges.

On the public Neapoli–Agios Nikolaos section, the first 10 kilometres are expected to be delivered to traffic in the near future. The bypasses of Chania, Rethymno and Heraklion are also among the first sections expected to open.

Road-safety upgrades continue

Alongside the new motorway construction, extensive safety interventions are being carried out on the existing road network. The measures include resurfacing, new signage and road markings, safety barriers, lighting, vegetation clearance and other improvements.

A total of 131 kilometres of road-safety works are planned between Kissamos and Heraklion. Authorities say the measures aim to reduce dangerous head-on collisions and improve protection for drivers until the new BOAK sections are completed.

Dimas acknowledged that land expropriations and cadastral issues may create challenges, but said the relevant ministries and agencies are working together to limit delays and keep the project moving.


Sources:
Creta24: Kastelli Airport construction site tour and statements from Dimas and Tachiaos
Nea Kriti: “New step for Kastelli Airport: Contract signed for the systems”
Cretalive: “New Kastelli Airport: Construction of the tunnel connecting it with BOAK progresses”
Fonien.gr: “Christos Dimas: Work progresses along the entire length of the BOAK”
Rethemnos News: “Christos Dimas: Work progresses along the entire length of the BOAK”
Nea Kriti: “BOAK: Dimas satisfied with the progress of the works”

Oval%403x 2

Don’t miss the daily tips and news about Crete!

We don’t spam! Read our privacy policy for more info.

Leave a Comment

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Scroll to Top