Construction work BOAK
Construction work for the new BOAK near Agios Nikolaos.

The ambitious project to modernize the Northern Road Axis of Crete (BOAK) has reached a critical turning point. Starting tomorrow, May 5, the Greek state begins the legal battle to secure the land necessary for the Heraklion-Chania section, a move that is already sparking debate over property rights and potential project delays.

The Legal Timeline

The first court hearings for the compulsory expropriations are scheduled for May 5, with a second major court date following closely on May 12. These hearings are essential for the state to gain control of the land required to transform Crete’s main artery into a modern motorway.

However, the process is not without its critics. The Greek State has chosen to split the expropriation process into 13 different files rather than unifying the case. Experts from the Technical Chamber of Greece (TEE) warn that this “fragmented” approach is a significant risk. Similar tactics in the eastern section of the BOAK (Lasithi) led to major delays and forced the state to pay compensation to contractors for “idle time.”

“Seize Now, Pay Later”: The Article 7A Controversy

In a move to speed up construction, the State is invoking Article 7A of the Code of Compulsory Expropriations. This specific legal tool allows the government to:
* Evict current property owners.
* Install the project contractor immediately.
* Commence construction work before the full compensation is paid to the owners.

While this fast-tracks the engineering phase, it has raised constitutional concerns regarding the protection of private property. Under this rule, the State will deposit only 70% of the “objective value” (tax value) of the property into a deposit fund.

The catch? The objective value is frequently much lower than the actual market value. Furthermore, owners cannot collect this money immediately; they must undergo a separate judicial process to be recognized as legal beneficiaries.

Focus on Rethymno

The first wave of expropriations will primarily affect the Rethymno region. Property owners in the following communities should be on high alert:
* Episkopi, Gerani, and Prines
* Atsipopoulo and Rethymno city outskirts
* Maroulas, Pangalochori, and Chamalevri
* Prinos, Adele, and Pigi

Local Frustrations

Local officials and TEE members have repeatedly called for the establishment of a dedicated Expropriation Office in Crete to handle these complex cases locally. However, the Ministry has recently dismissed these requests, stating that such an office is unnecessary—a stance that has frustrated many who fear that administrative errors in the 13 separate files could lead to years of unpaid claims, as seen in previous projects in Malia and Tarmaros.

What’s Next?

As the court proceedings begin this week, the eyes of the island are on the judiciary. The success of these hearings will determine whether the BOAK project stays on track or hits a legal roadblock that could stall Crete’s most important infrastructure project for years to come.

Rethemnos News

Oval%403x 2

Don’t miss the daily tips and news about Crete!

We don’t spam! Read our privacy policy for more info.

Leave a Comment

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Scroll to Top