Newsflash from Sunday, 6 September 2026:
Travelers driving along Crete’s northern coastal highway should prepare for daily traffic disruptions this week. The existing BOAK (Voreios Odikos Axonas Kritis — the Northern Road Axis of Crete) will be closed to regular traffic between Agios Nikolaos and Neapoli, two popular towns in the Lasithi region of eastern Crete, from Monday through Saturday.
Why is the road closing?
According to the contractor ΑΚΤΩΡ (Aktor), the closures are due to unexpected geotechnical conditions discovered during excavation works.
The problem area is located at kilometer marker 8+300 of the project, near the Xiropotamos bridge (Greek: “Ξηροπόταμος,” meaning “dry river”).
Crews need to remove unstable rock masses from the site to make the area safe for continued construction and future traffic.
Closure schedule
The road will shut down daily from 9:00 AM to 5:00 PM on the following dates:
- Monday, September 7, 2026
- Tuesday, September 8, 2026
- Wednesday, September 9, 2026
- Thursday, September 10, 2026
- Friday, September 11, 2026
- Saturday, September 12, 2026
Alternative routes for cars and buses
Small vehicles and buses will need to take detours during the closure hours.
From Neapoli to Agios Nikolaos: drivers should follow the Old National Road, then continue through Lakonia and the Kritsa junction before reaching Agios Nikolaos.
From Agios Nikolaos to Neapoli: the Old National Road is the only available route during closure hours.
What about heavy vehicles?
Heavy vehicles (trucks and large transport) will continue using the existing BOAK route.
However, their passage will be periodically interrupted throughout the day as work crews open and close the road at intervals.
What does this mean for visitors?
If you’re renting a car or driving between Agios Nikolaos and Neapoli this week, plan your trip outside the 9 AM–5 PM window whenever possible to avoid the detour.
If you must travel during those hours, expect a longer journey via the Old National Road, especially when heading toward Neapoli, since it’s the only option in that direction.
Bus schedules may also be affected, so check with local operators before heading to a bus stop along this route.
Give yourself extra time, particularly if you have a flight, ferry, or other time-sensitive appointment in Agios Nikolaos or Neapoli.
Signage should be in place, but if you’re unfamiliar with the area, using GPS navigation for the alternative route is recommended.
97 Million Euro Payout Adds to BOAK’s Mounting Bill — Here’s What’s Behind It

Crete’s most ambitious infrastructure project, the BOAK (Voreios Odikos Axonas Kritis — the Northern Road Axis of Crete), is facing yet another costly setback.
A newly approved ministerial decision authorizes a compensation payment of up to 97 million euros to the contractor building the Hersonissos–Neapoli section of the highway, sparking fresh political debate over the project’s spiraling costs.
Who is getting paid, and why?
The payment goes to “Pasifai Odos S.A.,” the private partner responsible for constructing the Hersonissos–Neapoli stretch under a public-private partnership (PPP) contract.
The contract was signed on April 21, 2023. According to opposition lawmakers, the government rushed to sign the agreement before that year’s elections without first completing necessary land expropriations.
Because the state failed to hand over construction sites on time, the contractor was awarded compensation for resulting delays and losses — now totaling 97,009,450 euros.
A major timeline shift
The delay tied to this compensation amounts to 447 days.
The Hersonissos–Neapoli section was originally scheduled for completion on April 21, 2027. That date has now been pushed back to July 11, 2028.
For the full 14-kilometer stretch of road, the overall delivery date has shifted to October 30, 2027, following a 487-day extension.
The bigger financial picture
The original investment cost for the Hersonissos–Neapoli section was estimated at 340.7 million euros.
Opposition politicians argue that once public financial contributions and long-term availability payments (extending all the way to 2053) are factored in, the true cost balloons to 755 million euros.
Add the new 97 million euro compensation, and the total visible fiscal burden reaches approximately 852 million euros, according to critics.
Recovery Fund contribution reduced
Katerina Spyridaki, a Lasithi region MP for the PASOK–Kinima Allagis party, has filed a parliamentary question alongside colleagues Eleni Vatsina, Pavlos Gerouianos, and Tasos Nikolaidis, demanding transparency on the project’s finances.
Their inquiry reveals that on August 4, 2026, the EU Recovery and Resilience Facility’s contribution to the Hersonissos–Neapoli section was reduced from 90 million euros to 56.999 million euros — a cut of roughly 33 million euros.
Crucially, this funding cut does not reduce the project’s actual cost. The missing 33 million euros must now be covered through other financing or national public funds.
Neapoli–Agios Nikolaos section also affected
A similar pattern appears in the neighboring Neapoli–Agios Nikolaos section (a coastal town in Lasithi, eastern Crete).
Originally expected to be completed in September 2025, this section’s timeline has also slipped to October 30, 2027.
Expropriation costs for this stretch rose from 11.55 million euros to about 18.55 million euros, while roughly 38 million euros were cut from Recovery Fund financing.
Additional compensation and expenses linked to delays, land handovers, archaeological finds, environmental changes, and accelerated works are now approaching 50 million euros for this section alone.
Government response
Minister of State Akis Skertsos has pushed back against criticism over funds being removed from the Recovery and Resilience Facility.
He argues the Fund isn’t a rigid checklist but a milestone-based mechanism, and that only a small portion of the technically and financially complex BOAK project was ever meant to remain within it.
Skertsos insists this does not mean the project is being cancelled, citing the EU’s joint Canadair aircraft purchase as a comparable example of shifting funding mechanisms.
What critics are demanding
Opposition lawmakers argue that a properly planned project should not require signing contracts before expropriations are finalized, nor should completion dates shift by hundreds of days.
They stress that the ultimate goal must be a single, uninterrupted BOAK highway stretching from Kissamos (western Crete) to Sitia (eastern Crete), with a meaningful connection to Ierapetra on Crete’s southern coast.
According to Spyridaki, treating Neapoli or Agios Nikolaos as the “finish line” ignores the needs of the island’s more remote eastern communities.