The new Kastelli Airport in Crete is currently 75% complete — but according to the mayor of the local municipality, that doesn’t mean it will open anytime close to the official target date.
Vasilis Kegeroglou, mayor of Minoa Pediada (a municipality in the Heraklion region near the airport construction site), says the airport may remain closed well beyond November 2028, even if construction itself finishes on schedule.
A Scenario Nobody Wants: Finished But Closed
The article raises an unusual possibility: that the airport’s physical construction could be completed by 2027 or early 2028, while the facility stays “locked” — unable to receive passengers or airlines — for a year or two afterward.
This gap between construction completion and actual commercial operation is at the heart of the timeline concerns.

Why the Delay? It’s All About the Radar
Test flights, planned by the contractor for 2027, cannot happen without fully functioning radio navigation aids — essentially, the airport’s radar systems.
Here’s where the math gets complicated:
- The contract for installing the radar equipment was signed in August 2026.
- Official timelines indicate the installation requires 27–28 months to complete (though it could potentially be faster).
- Counting forward from August 2026, that puts completion around autumn 2028 — at the very earliest.
- As of the writing of the source article, two months after signing, no substantial radar installation work had yet begun.

Archaeological Work Must Come First
Adding another layer of complexity, a 2025 decision by the Central Archaeological Council (KAS) — Greece’s body overseeing archaeological matters — requires that excavation and restoration work be completed at a monument on Papoura Hill before any radar can be installed there.
The sequence required is strict: first excavation, then restoration, and only then can radar installation begin.
According to the timeline:
- Excavations are expected to finish by spring or summer 2027.
- Restoration work will follow, requiring at least one additional year (assuming no bureaucratic delays).
This raises an important question: when exactly does the 27–28 month radar installation clock actually start, if the site isn’t even ready for radar work until after restoration is complete?

Legal Challenges Add Further Uncertainty
The Municipality of Minoa Pediada had filed a legal challenge against the KAS decision allowing radar installation on Papoura Hill, but the Greek Council of State (ΣτΕ) rejected that appeal.
The municipality is now waiting for the official written ruling before deciding on next steps — and further legal challenges, potentially even reaching the European Court of Human Rights in Strasbourg, haven’t been ruled out.
Other Factors Piling Up
Beyond the radar and archaeological issues, several other ongoing projects could add to delays:
- Flood-prevention works for nearby settlements, still at the preliminary design stage
- An access tunnel currently under construction
- Airport electrification work, including relocating overhead and underground power lines from Kokkini Hani and Chersonissos (coastal areas near Heraklion) — a €43 million project taken on by the contractor after Greece’s power grid operator, ADMIE, was unable to handle it
- A secondary radar installation in the Asterousia Mountains (southern Crete), which received approval last summer
There’s also the matter of transitioning operations smoothly from the current Heraklion airport, “Nikos Kazantzakis,” to the new Kastelli facility — a process that itself requires adequate planning time.

The Mayor’s Blunt Assessment
When asked directly about the timeline, Mayor Kegeroglou offered a simple but telling response: “From 2029 onward…”
He didn’t specify exactly how far past 2029 the opening might slip — suggesting that even he isn’t certain how long the wait will ultimately be.

What Does This Mean for Visitors?
If you’re planning travel to Crete in the coming years, don’t count on flying directly into the new Kastelli Airport anytime soon.
- Continue expecting to use the current Heraklion Airport (“Nikos Kazantzakis”) for commercial flights, likely through 2028 and possibly into 2029 or later.
- If you’re involved in long-term travel planning or property investment near the new airport site, factor in this extended timeline — construction progress doesn’t guarantee an operational date.
- Keep an eye on local news for updates, since further legal appeals or bureaucratic issues could push the opening even later than current estimates.
- Don’t be misled by headlines about “75% completion” — as this report shows, finishing construction and actually opening for commercial flights are two very different milestones.