More than 35% progress in the construction of the new airport for Heraklion in Kastelli: the project reaches a significant milestone.

Construction of a new airport
Construction of a new airport.

More than 35% progress in the construction of the new airport for Heraklion in Kastelli

The construction of the new international airport at Kasteli Heraklion has reached a significant milestone. The project, managed by the GEK Terna-GMR consortium, has completed a third of its planned works, marking over 35% overall project completion. This development includes substantial progress in various key areas such as the terminal, runways, auxiliary buildings, and parking facilities.

The progress at the airport terminal has been notable. The main terminal building’s structural framework is over 90% complete. The same diligence is seen in the construction of auxiliary spaces and buildings, as well as parking facilities. This work is crucial for ensuring smooth operations once the airport is functional.

Key Areas of Construction

  1. Runways and Taxiways:

    • Surface Works: Ongoing construction focuses on the final surfaces for both runways and taxiways.
    • Aircraft Parking Areas: Grading and surface preparation have advanced considerably, making significant headway in the aircraft parking zones.
  2. Terminal Buildings:

    • Main Terminal: Structural works are nearly finished, particularly the main load-bearing structures.
    • Police Building: Almost at completion, this facility is integral to the airport’s security framework.
  3. Fuel Distribution Network:

    • Underground Storage: Installation of the fuel storage infrastructure, essential for aircraft refueling, is progressing well.
    • Distribution Systems: Laying down the pipeline network for efficient fuel distribution to aircraft has begun.
  4. Road Connections:

    • BOAK and NOAK: Significant advancements in the road networks connecting the airport to key motorways (NOAK is 77% complete; BOAK is 48% complete). Specifically, BOAK involves constructing an 18-kilometre stretch featuring dual lanes for each traffic direction.

Facilities and Infrastructure

Central Terminal Building:

  • Nearly completed structural works.
  • Extensive underground utility installations, including mechanical and electrical systems.
  • Construction of the departures bridge has commenced.

Auxiliary Spaces:

  • Fuel tank storage area approaching final stages.
  • Biological waste treatment plant construction is underway.

Police Station:

  • Building’s finalisation is imminent, enhancing the security measures in preparation for the airport’s operation.

Control Tower:

  • Foundation completed with ongoing construction of the tower and supporting facilities.

Operational Implications

The new airport at Kastelli, being one of the flagship projects for Greece’s infrastructure improvement, promises to bolster regional and national air transport capabilities. The completion timeline has set expectations for the major segments to be finished by 2025, with full operational readiness anticipated by 2026. The relocation and transitioning of operations from the current Nikos Kazantzakis Airport to the new facility will follow, ensuring minimal disruption.

Key Milestones Achieved

  • Terminal and Auxiliary Buildings: Significant milestones include the structural completion of main and auxiliary buildings.
  • Runways and Taxiways: Ongoing work with a focus on final surface preparations.
  • Supporting Infrastructure: Key utilities such as fuel distribution networks and waste treatment facilities making considerable progress.

Construction and Logistics

  • Excavation and Grading: Major earthworks have been completed, setting the stage for subsequent construction phases.
  • Road Infrastructure: Road links are being developed to ensure swift connections to the broader transport network, enhancing accessibility and operational efficiency.

Economic and Strategic Importance

The new airport is expected to play a pivotal role in the economic development of Crete, providing enhanced connectivity for passengers and freight. The project’s strategic placement bolsters its importance in revamping Greece’s air transport landscape, supporting both tourism and commercial activities.

Sensational New Finds During Airport Construction on Crete

Excavation work for the new international airport in Heraklion, Crete has led to some astonishing discoveries. While preparing the construction site, workers unearthed significant archaeological remains that captured the attention of experts and the public alike.

The recent find is described as unique and significant in its historical context. The location of the discovery is on a hill known as Papoura, where a radar station was originally planned. Instead, remnants of an ancient Minoan structure were uncovered, offering a glimpse into Crete’s rich past. This unexpected discovery halted the radar station plans as archaeologists rushed to examine the site in detail.

Key Details:

  • Location: Hill Papoura, near the village of Kastelli
  • Discovery: Ancient structure remains
  • Planned Construction: Radar station

Archaeologists emphasised the need for thorough examination of the site to understand the significance of the find. They believe that these remains could shed light on an undisclosed period of Crete’s history. The excavation and preservation of the site will offer valuable insights and is now a priority alongside the airport’s construction.

Impact on Construction:

The discovery has had a considerable influence on the ongoing construction. The project, which was more than 35% complete, had to adjust its plans to ensure the protection of these archaeological assets. The completion timeline and layout had to be revised without compromising the integrity of the historical site.

Efforts are now being made to balance the rapid progress of the airport’s construction with the careful preservation of these important archaeological finds.


Frequently Asked Questions

What advancements have been made in the construction of the new Heraklion Kastelli Airport?

Construction of the new Heraklion Kastelli Airport has progressed significantly, with more than 35% of the work already completed. The ongoing developments include the terminal, runways, and road links surrounding the airport.

When is the new airport in Kastelli, Heraklion expected to be completed?

The anticipated completion date for the new Kastelli, Heraklion airport is not explicitly stated, but with construction already advanced past 35%, significant milestones are expected in the coming months.

Which companies are participating in the Kastelli Airport development project?

The companies involved in developing the Kastelli Airport project include GEK TERNA and GMR. These firms have been key players in moving the construction forward efficiently.

Are there any job openings currently available at the new Heraklion Kastelli Airport?

Employment opportunities at the new Heraklion Kastelli Airport will likely arise as the project progresses further. Job seekers should keep an eye on the project’s official announcements and local job boards for updates.

What impact will the new Kastelli Airport have on Crete’s tourism sector?

The new Kastelli Airport is expected to have a positive impact on Crete’s tourism industry. Improved facilities and increased capacity will likely attract more visitors, boosting the local economy.

How will the new Heraklion Kastelli Airport offer better facilities than the current ones?

The new Heraklion Kastelli Airport is set to provide enhanced facilities compared to the existing airports. With a state-of-the-art terminal, extended runways, and new road connections, it aims to offer a more efficient and comfortable travel experience for passengers.

Oval@3x 2

Don’t miss the daily tips and news about Crete!

We don’t spam! Read our privacy policy for more info.

Leave a Comment

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Scroll to Top

Don’t miss the daily tips and news about Crete!

We don’t spam! Read our privacy policy for more info.