A major shift in Crete’s air travel infrastructure is being carefully mapped out, and the clock is now ticking. Officials have unveiled the roadmap for transitioning operations from Nikos Kazantzakis Airport (Heraklion’s current international airport) to the new facility being built at Kastelli, a site in central Crete.
The plan was presented at a briefing held in Heraklion, organized by IAHC (International Airport Heraklion Crete), the company overseeing the new airport’s operations.
A Carefully Staged Transition
More than 50 representatives attended the event, including airline officials, companies operating at the airport, public authorities, and other stakeholders. The goal: ensure everyone involved understands what needs to happen before the first aircraft lands at the new Kastelli facility.
The ambition is for the new airport to be fully operational from day one — with no disruptions to passengers or airlines during the switch.
To achieve this, officials outlined a detailed familiarization process, allowing all parties to become thoroughly acquainted with the new airport’s facilities, procedures, and operational systems. As one speaker put it, every single detail — down to the last screw — needs to be in place before the big move happens.

Timeline: Training Begins September 2027
According to the plan, preparations will officially begin in September 2027, nearly 14 months before the targeted switch.
The timeline includes an extensive training program for everyone involved in the new airport’s operations. Training sessions are scheduled to run twice a day, three days a week, ensuring staff and partner organizations fully understand their roles and responsibilities at the new facility.
The goal is to identify and resolve any potential issues well in advance — with full readiness targeted for November 2028.
Moving the Equipment
Once training is underway, attention will turn to physically relocating equipment and the infrastructure necessary for the new airport to function. This logistical operation is scheduled to take place toward the end of the tourist season, specifically to minimize disruption to Nikos Kazantzakis Airport’s existing operations during peak travel months.
To manage this complex process, a dedicated task force will be formed, bringing together experts with experience in similar airport relocations and transitions from other countries. Officials say this international know-how will help ensure each stage of the transition is properly planned and tested before the historic first landing at Kastelli.

Official Statements
The framework guiding this process is known as ORAT — Operational Readiness, Activation and Transition — a standardized program used internationally to prepare new airports for launch.
During the briefing, attendees were shown a 3D visualization of the new airport alongside updates on construction progress.
Nikos Anastasiou, CEO of IAHC, addressed the audience directly, highlighting the importance of collaboration with the airport’s future users — the airlines and service providers who will operate there daily.
“We are beginning a dialogue that we hope will be constructive and honest, aimed at determining what needs to be done to ensure the smooth Operational Readiness and Transition process (ORAT), as well as smooth operations going forward,” Anastasiou said. “We are committed to being direct and transparent about what is feasible, realistic, and achievable, and I am confident that together we will find the best possible solution for every obstacle and challenge ahead.”
What does this mean for visitors?
- No immediate changes: Nikos Kazantzakis Airport remains fully operational, and this transition planning does not affect current travel to Crete.
- Timeline to watch: Major preparations begin in September 2027, with full readiness targeted by November 2028 — keep this in mind if booking travel for late 2028 or beyond.
- Expect updates over time: As the transition date approaches, more specific details about flight schedules, airport closures, or operational changes are likely to be announced.
- Equipment relocation period: The physical move of airport infrastructure is planned for the end of a tourist season, meaning minimal disruption is expected during peak travel months.
- Stay informed: Travelers planning trips to Crete in 2028 or later should monitor official airport announcements as the transition date draws closer.
While the shift to Kastelli remains more than two years away, this briefing marks the first major public step in coordinating what promises to be one of the most significant infrastructure changes in Crete’s recent history.
Source: Patris.gr