Newsflash from Sunday, 12 July 2026:

Drivers in eastern Crete should plan ahead as a temporary closure of the BOAK (Northern Road Axis of Crete) will affect traffic between Agios Nikolaos and Neapoli on Monday, July 13 and Wednesday, July 15 (9:00 – 17:00 hrs). The disruption is expected to last for several hours during the day, requiring motorists to follow alternative routes.
How Traffic Will Be Managed
During the closure period, traffic will be redirected as follows:
- From Neapoli to Agios Nikolaos (small vehicles and buses): Traffic will be diverted via the Old National Road, passing through Lakonia and the Kritsa junction before reaching Agios Nikolaos.
- From Agios Nikolaos to Neapoli (small vehicles and buses): Vehicles will travel exclusively via the Old National Road.
- Heavy vehicles: Trucks and other large vehicles will continue to use the BOAK, with periodic pauses in construction work allowing the road to reopen intermittently במהלך the day.
What Drivers Should Expect
Motorists are advised to expect delays, especially during peak hours, and to follow posted signage and instructions from traffic authorities. Using alternative routes and allowing extra travel time will help reduce inconvenience.
The temporary measures are part of ongoing works aimed at improving road safety and infrastructure in the area.
Plan Ahead
If you are traveling between Agios Nikolaos and Neapoli on the affected dates, consider adjusting your schedule or route in advance. Staying informed and patient will ensure a smoother journey for everyone.
BOAK Update: 70% of Neapoli–Agios Nikolaos Set for Summer Opening, But Full Completion Pushed to 2027

The development of the Northern Road Axis of Crete (BOAK) in the Lasithi region is currently a “tale of two speeds.” While motorists can look forward to using a significant portion of the new motorway this summer, the full completion of the Neapoli–Agios Nikolaos section has faced a major setback, with the final deadline now pushed back to late 2027.
The Good News: 10.2 Kilometers Opening Soon
According to recent updates from the Ministry of Infrastructure and the contractor (AKTOR), the project is preparing to deliver the first 10.2 kilometers of the new road during the current summer season. This represents roughly 70% of the total 14.5-kilometer project.
This new segment is expected to drastically improve road safety. It features:
- Two lanes of traffic per direction.
- An Emergency Lane (LEA) on both sides.
- A central safety barrier.
- A total road width of 22.5 meters.
The rush to complete this section is tied to the strict deadlines of the Recovery Fund, which requires specific milestones to be met by July 2026.
The Delay: Why 2027?
Despite the progress on the main stretch, the “finish line” for the entire project has been moved. Originally slated for completion in September 2025, a 487-day extension has been granted, moving the final delivery date to October 30, 2027.
The delay is not attributed to the contractor but rather to several “thorny” administrative and technical issues, including:
- Expropriation Hurdles: Significant delays in the state handing over land to the contractor.
- Utility Relocations: Complex moves for electricity (DEDDIE) and water (DEYA) networks.
- Urban Planning: Issues regarding the town plan of Neapoli.
- Archaeological Challenges: Technical difficulties involving the relocation of traditional mills and other archaeological concerns.
Due to these state-side delays, the contractor has been awarded over €20.1 million in compensation for “positive damages,” increasing the overall cost of the €157 million contract.
A Two-Tiered Funding Strategy
To protect the project’s financing, the Ministry of Infrastructure has split the project into two phases. The first 10.2 km will remain under the Recovery Fund (must be finished by July 31, 2026), while the remaining, more complex sections—including the difficult Agios Nikolaos bypass—will be moved to National Funding with the new 2027 deadline.
While the opening of the first 10 kilometers will provide immediate relief to drivers, local residents and officials in Lasithi continue to call for more transparency and consistent updates to ensure no further “surprises” arise on the long road to completion.