Completion of the Chersonissos-Neapoli section not before July 2028, due to delays in expropriations. New completion date for the Neapoli–Agios Nikolaos section set for 30 June 2026.

Description of the Project
The project targets the middle section of the BOAK motorway, focusing on the stretch between Hersonissos and Neapoli.
It’s a pretty big deal for Crete, aiming to boost road safety and ease traffic on this busy route.
This section requires building multiple tunnels, some using the cut & cover method.
Those tunnels should help drivers avoid rough terrain and shave some time off the trip.
New road segments and related infrastructure are also part of the plan.
The contract follows a public-private partnership (PPP) model.
AKTOR-GEK TERNA leads as the main contractor, while the contracting authority keeps an eye on everything to make sure it all lines up with the agreement.
They kicked things off after signing the contract in April 2023.
The original plan called for all the necessary land to be handed over by April 2024.
But things hit a snag—delays in getting expropriated land slowed everything down.
These setbacks pushed the service availability date back from April 21, 2027, to July 11, 2028.
The public’s late land delivery counts as a compensable event, at least according to the contract.
The consortium has now asked for a 16-month extension and wants 124 million euros to cover costs from the delay.
An independent auditor checked out the new schedules to confirm what caused the holdup and how big it really is.
Funding from the Recovery Fund is also in play, aiming to bring the infrastructure up to modern European standards.
Key facts:
Aspect | Details |
|---|---|
Project Section | Hersonissos – Neapoli (middle part of BOAK) |
Main Contractors | AKTOR – GEK TERNA consortium |
Contract Type | Public-Private Partnership (PPP) |
Original Service Availability Date | 21 April 2027 |
Revised Service Availability Date | 11 July 2028 |
Delay Causes | Late delivery of expropriated land |
Compensation Requested | 124 million euros |
Construction Techniques | Tunnels (cut & cover included), new road segments |
Funding Source | Recovery Fund |
New completion date announced for the Neapoli–Agios Nikolaos motorway: 30 June 2026

The long-awaited Neapoli–Agios Nikolaos section of Crete’s northern road axis (BOAK) has a new official completion date: 30 June 2026. According to a recent decision by the Ministry of Economy and Finance, the project schedule has been extended to ensure that the final result meets the highest standards of safety, quality and functionality.
This extension, which is part of the third amendment to the construction contract, reflects the need for technical adjustments that have arisen during the construction process. While some may view the new deadline as a delay, those responsible emphasise that it is a realistic and necessary adjustment that will ultimately result in a safer and more modern road for residents and visitors.
Key project features
– Total length: 14.5 kilometres
– Design: Two lanes in each direction plus an emergency lane (LEA)
– Total width of the road: 22.5 metres with a central safety barrier
– Funding: €137 million from the Recovery and Resilience Facility (RRF)
– New completion date: 30 June 2026
Technical innovations and local benefits
The revised plan includes targeted measures to modernise essential infrastructure. These include:
– Relocation of utility networks with an additional budget of €337,200
– A new sub-project for the relocation of irrigation networks led by T.O.E.B. Merambellou, financed with €615,000 to ensure that the new road improves local agricultural systems rather than adversely affecting them.
Once completed, the new motorway will significantly reduce travel time between Neapoli and Agios Nikolaos and eliminate three dangerous bends that have long posed a safety risk. The improved design is expected to drastically reduce the accident rate and provide a more pleasant driving experience.
Strategic importance for eastern Crete
The project also includes extensive improvements to intersections, such as the Xirokampos motorway junction, which will improve connections to Elounda, Kritsa, Ierapetra and Sitia. These improvements will boost both tourism and agricultural transport, thereby stimulating the regional economy.
The neighbouring Hersonissos–Neapoli section, which is being built as part of a public-private partnership (PPP) led by GEK TERNA and AKTOR Concessions, will continue as planned. Once both sections are completed, the unified management model will ensure consistent maintenance and uniform operation throughout the eastern BOAK corridor.
A road to the future
The Neapoli–Agios Nikolaos project is more than just a motorway – it is an important investment in Crete’s connectivity, safety and long-term development. With the new completion date set for June 2026, the region is moving closer to realising a modern, efficient and resilient transport network that will serve future generations.
BOAK: A Road of High Risk – Traffic Police Checks and Driver Responsibility

The Northern Road Axis of Crete (BOAK) in the Lasithi area plays a huge role in the local economy and daily life. It’s the main route for tourists, agricultural transport, and residents heading to work or just going about their day.
Even with some ongoing upgrades, the road still feels risky. Both the authorities and drivers really need to stay alert.
Traffic Police based in Neapoli handle enforcement on VOAK within Lasithi. Their job matters—a lot—when it comes to keeping the road safer and cutting down on accidents.
Officers don’t just wave people through; they check vehicles thoroughly, especially if there’s hazardous cargo involved. They’re trying to head off trouble before it starts.
But, let’s be honest, safe driving mostly comes down to the person behind the wheel. Authorities keep saying it: excuses just don’t cut it.
Drivers have to adapt to whatever the road throws at them and stick to traffic laws, no matter how tempting it is to bend the rules.
Some of the big traffic violations police focus on are:
- Driving under the influence of alcohol
- Not wearing seat belts or helmets
- Using mobile phones while driving
- Speeding
Honestly, these actions crank up the risk of serious accidents. Police also get pretty frustrated when people tip off drivers about upcoming checkpoints—it’s not just annoying, it actually shields risky behavior.
Let’s clear up a common misconception: officers don’t pocket the fines from these controls. The money goes to local authorities for keeping the roads in shape and making them safer.
So, there’s a direct connection between fines and improving driving conditions, even if it doesn’t always feel that way in the moment.
Responsibility | Details |
|---|---|
Drivers | Must adapt behaviour to conditions; no tolerance for risky actions |
Police | Conduct regular, specialised checks, especially on trucks carrying dangerous goods |
Public | Should avoid warning others of police checks to support enforcement |
Authorities | Use fines to fund road safety and repairs |