Double trouble on the BOAK in Crete: the Agios Nikolaos–Neapoli route will be completely closed for several days on two separate occasions in September

Businesspeople, residents and visitors at their wits’ end, and compensation for property owners affected by BOAK expropriations.

BOAK sperrung

Double Trouble on Crete’s BOAK: Agios Nikolaos–Neapoli Route to Shut Twice in September

Drivers in eastern Crete are bracing for a second wave of disruption, as the BOAK (Voreios Odikos Axonas Kritis — the Northern Road Axis of Crete, the island’s main coastal highway) will close completely not once, but twice this September.

The affected stretch runs between Neapoli and Agios Nikolaos, two towns in the Lasithi region of eastern Crete, and falls within the highway’s ongoing reconstruction zone.

Two closures, one difficult month

According to an announcement by the Lasithi Police Directorate, the highway will be fully shut to traffic on the section between kilometre marker 187 (Neapoli junction) and kilometre marker 197 (Xirokambos junction) during two separate periods.

The first closure runs from 6:00 am on Thursday, September 17 until 6:00 am on Monday, September 21, 2026, for demolition work on the T6 bridge.

The second closure follows just days later, from 6:00 am on Friday, September 25 until 6:00 pm on Tuesday, September 29, 2026, this time for demolition works on the T5 bridge, specifically the high bridge at Xiropotamos (km 8+300).

The contractor carrying out the project has confirmed both closures, meaning drivers face two rounds of major detours within less than two weeks.

Detour routes for vehicles

Vehicles weighing up to 12 tonnes — including cars and buses — will be diverted onto the Old National Road (Palaia Ethniki Odos).

  • Travelling from Agios Nikolaos towards Heraklion: via the Old National Road.
  • Travelling from Neapoli towards Agios Nikolaos: via the Old National Road, then through Lakonia and the Kritsa junction.

Heavy vehicles over 12 tonnes face a much longer detour via the Southern Road Axis, through the provincial road connecting Ierapetra and Viannos (Heraklion), and vice versa.

Local reaction: “an economic catastrophe”

The timing has caused alarm among tourism professionals, as the closures fall during a period when eastern Crete still receives significant numbers of international visitors.

Giorgos Pelekanakis, president of the Panhellenic Federation of Hoteliers, said the works could have waited until mid-October, when tourist numbers typically decline, allowing the project to proceed with far less disruption.

He also described daily scenes of tour bus drivers arriving at hotels frustrated and delayed, with some guests anxious about missing flights due to the extended travel times.

Stratos Magkousakis, president of the Association of Tourist Bus Owners of Crete, estimated that the detour via the Old National Road adds roughly one extra hour of travel time, particularly on the Heraklion–Agios Nikolaos direction. He noted the added difficulty for large vehicles having to navigate narrow village roads.

Zacharias Doxastakis, mayor of Chersonisos (a coastal municipality in Heraklion), expressed concern over the timing of the works and called for additional staffing on other project fronts to speed up completion, citing significant disruption to the local economy and community.

Compounding the problem, the wider BOAK corridor between Heraklion and Chersonisos is already experiencing heavy congestion due to separate roadworks extending to the Karteros area, with delays there reportedly reaching up to an hour during peak times.

What does this mean for visitors?

  • Plan extra travel time — expect delays of up to an hour or more if travelling between Heraklion and Agios Nikolaos during either closure period.
  • September 17–21: avoid the Neapoli–Agios Nikolaos section of the BOAK entirely; use the Old National Road detour instead.
  • September 25–29: the same section closes again — factor this into any planned road trips or airport transfers during this window.
  • Travelling by car or taxi (under 12 tonnes): follow the Old National Road, via Lakonia and Kritsa junction if heading from Neapoli to Agios Nikolaos.
  • Travelling by coach, truck, or heavy vehicle (over 12 tonnes): expect a significantly longer detour via Arkalochori, Viannos, and Ierapetra.
  • Heading to or from the airport: build in extra buffer time, especially during the closure windows, to avoid missing flights.
  • Follow road signage and traffic personnel carefully, as the detour routes pass through narrower local roads not designed for heavy traffic volumes.

With eastern Crete still in the middle of its tourist season, local officials continue to raise concerns about the impact of scheduling these works during September rather than waiting for the quieter autumn months.

€6.9 Million Compensation Fund Released for Landowners Affected by New BOAK Expropriations

BOAK Agios 2026
The BOAK roadworks begin shortly after Agios Nikolaos.

Property owners whose land was expropriated for the construction of the new BOAK (Voreios Odikos Axonas Kritis — the Northern Road Axis of Crete) are finally set to receive their long-awaited compensation payments.

The Greek Ministry of Infrastructure and Transport has approved a payment of €6.9 million for expropriated properties along the Neapoli–Agios Nikolaos section of the highway, both towns located in the Lasithi region of eastern Crete.

Money now moving to owners’ accounts

The funds have already been deposited with the Deposits and Loans Fund (Tameio Parakatathikon kai Danion) in Athens, and payments are now being transferred directly into the bank accounts of eligible landowners.

This comes after years of waiting for many of the affected property owners.

The compensation relates specifically to what is known as Zone C of the expropriations for this highway section — covering the stretch from kilometre marker 8+900 to kilometre marker 12+400, from the Lakonia junction through to the last fuel stations along the route.

In total, around 50 to 55 beneficiaries will receive payments, including owners of land, houses, and businesses.

Importantly, these are described as final compensation amounts — not the initial estimated figures, which are often subject to errors, but the definitive sums confirmed following a fourth and final court ruling.

Legal fees also covered

Alongside compensation for property owners, the Ministry has also deposited funds to cover legal representation costs:

  • €75,224.91 for the Thessaloniki Bar Association
  • €12,634.46 for the Heraklion Bar Association

These amounts cover the lawyers who represented property owners with real estate rights or claims on the expropriated land.

A long road to resolution

The Zone C expropriation process faced significant delays due to errors and omissions in the original land registry (ktimatologio) records.

Numerous correction requests were filed, and on-site inspections were carried out, but the findings were not incorporated into a revised registry in time. This led to a court order (Decision 255/6.11.2023 of the Single-Member Court of Appeal of Eastern Crete) mandating corrections to numerous properties.

A first corrected land registry was compiled and approved on October 29, 2024, incorporating both the court’s ruling and the results of the various property inspections.

Rising costs for the project

The overall public expenditure for expropriations along the Neapoli–Agios Nikolaos section has increased substantially — from an original €11.55 million to €18.55 million.

Of this new total, approximately €12.95 million comes from Greece’s Recovery and Resilience Fund (Tameio Anakampsis).

The increase reflects new compensation calculations based on Decision 73/2025 of the Three-Member Court of Appeal of Eastern Crete, which set the final unit compensation rates for the affected properties, as well as associated legal fees.

The Neapoli–Agios Nikolaos section, built as a public project by contractor group AKTOR, was the very first section of the new Crete highway to be put under contract, four years ago. Part of this section is expected to be delivered to traffic in the near future.

Chania Landowners Fury as Greek State “Requisitions” Property for BOAK Highway Without Payment

Expressway
BOAK Expressway in western Crete (Chania).

Property owners in the Chania region (a regional unit on the northwest coast of Crete) are furious as the Greek State moves forward with what critics are calling an effective “requisition” of land for the new BOAK highway (Voreios Odikos Axonas Kritis — the Northern Road Axis of Crete).

The controversy centers on the accelerated expropriation process being used to secure land for the highway’s construction through several communities in the Apokoronas municipality, including Kalyves, Armenoi, Neo Chorio, Kaina, and Paidochori, as well as the local communities of Aptera and Tsikaliaria Soudas.

An urgent legal process with no room for objection

The Chania Bar Association (Dikigorikos Syllogos Chanion) held an informational meeting on Tuesday evening at the former town hall of Armenoi in Kalyves, Apokoronas, to brief affected landowners on how to navigate the process.

Agapi Mikrou, President of the Chania Bar Association, explained that on September 22, two applications filed by the Greek State against property owners will be heard in court, under what is known as the “7a” fast-track procedure of the expropriation code.

Unlike the standard expropriation process — where a preliminary price is proposed, arguments are heard, and a provisional court-set price is established before proceeding — this accelerated procedure requires landowners to hand over their properties without being paid first.

Instead, the State deposits an amount with the Deposits and Loans Fund (Tameio Parakatathikon kai Danion) that it unilaterally deems fair, based on its own valuation report.

Crucially, Mikrou stressed that this initial amount will not be determined or reviewed by the court on September 22, and there is no possibility of objection at this stage. The law allows this rapid process specifically because of the project’s urgent classification.

“Essentially, we are proceeding with a requisition of citizens’ properties,” Mikrou said, though she noted that a subsequent request for setting a provisional unit price will follow, at which point landowners’ legal representatives will contest the State’s valuation and argue for fairer compensation reflecting real local property values.

Errors in property records and unfair “self-compensation” rules

Mikrou highlighted that the property valuation tables contain numerous errors that need correcting before the process can proceed properly.

Beyond simple pricing disputes, she pointed to a particularly contentious rule known as “self-compensation” (autoapozimiosi). Under this rule, the State refuses to pay for certain square metres of land it takes, arguing that the remaining property increases in value because the new road passes through it — effectively claiming the owner is “self-compensated” by this rise in value.

According to Mikrou, this approach fails to properly account for the original size and value of each property, and it does not adequately consider cases where the remaining land is actually damaged or rendered less usable by the road construction — situations where owners should not be penalized with this deduction at all.

She noted this issue is especially significant in the Kalyves area, where the highway route passes directly through land included in the town’s official urban plan, rather than through simple agricultural plots.

Bar association steps in to fight for fair compensation

The Chania Bar Association has handled expropriation cases in the region for many years and plans to submit correction requests to the relevant authorities on behalf of affected owners collectively.

Lawyers will also gather comparative property value data to build a strong case for the upcoming hearing on provisional unit pricing, aiming to secure compensation that reflects fair market value.

Mikrou explained that, under Greek law, compensation should theoretically allow owners to replace their expropriated property with one of equal value — though she acknowledged this ideal is rarely achieved in full.

Regarding timing, she noted that similar cases from earlier BOAK sections were already heard in April and May of this year, suggesting some clarity on unit pricing could emerge within 2026 for the current Chania cases as well.


Sources:

RadioLasithi.gr

Patris.gr

NeaKriti.gr

Cretalive.gr

Zarpanews.gr

Oval%403x 2

Don’t miss the daily tips and news about Crete!

We don’t spam! Read our privacy policy for more info.

Leave a Comment

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Scroll to Top